How to Price a Roofing Job (2026)

The roof you bid isn't always the roof you find once the old one is off. Here's how to price by the square, protect yourself with a decking allowance, and quote a replacement that still profits after surprises.

Free tool

Price the roof by the square, add tear-off and a decking allowance, and export a clean PDF — free.

Open the roofing estimate tool →

Roofing is priced by the square, but the money is won or lost on the parts you cannot see until the tear-off: the decking, the layers, and the flashing. Here is how to build a roof replacement quote that survives what you find up there.

Step 1: Measure in squares and pick the material

A roofing square is 100 sq ft. Measure the roof area (not the floor), divide by 100 for your square count, and set your installed price per square by material. Confirm the count on final measurement.

Material (installed)UnitTypical 2026 cost
3-tab asphaltper square$300–$500
Architectural shingleper square$400–$600
Metalper square$500–$1,600
Tileper square$700–$2,500
Tear-off & removalper square$100–$500

Step 2: Price tear-off and count the layers

Removing the old roof and hauling it off is real cost — line tear-off per square and note how many existing layers you are removing, since a second or third layer adds labor and disposal. Add a dumpster line.

Step 3: Add a decking allowance for hidden rot

You cannot see rotted plywood until the roof is open. Put a per-sq-ft decking replacement rate in the estimate so replacing bad decking is priced, not argued. This single line turns the most common roofing surprise into a documented change order.

Step 4: Add accessories, markup, and a deposit

Underlayment, flashing, drip edge, and ridge vent are what make the roof last and the warranty hold — line them. Then add markup for overhead and profit, take a deposit to schedule, and provide your workmanship warranty in writing.

Example: a 25-square architectural roof installed at $450/square ($11,250), tear-off at $150/square ($3,750), and a $450 dumpster is $15,450 of work. With a 10% markup and tax on the dumpster, the quote lands near $17,030 — with about $5,100 as a 30% deposit.

Common pricing mistakes to avoid

Price by the square and protect yourself with a decking allowance. Start your next one in the roofing estimate tool.

Frequently asked questions

How much should I charge for a roof replacement?

In 2026, installed cost per square (100 sq ft) runs about $300–$500 for 3-tab asphalt, $400–$600 for architectural shingles, $500–$1,600 for metal, and $700–$2,500 for tile. Tear-off is about $100–$500 per square, labor $200–$300 per square, and deck replacement $2–$5 per sq ft.

What is a roofing square?

A roofing square equals 100 square feet of roof area — the unit roofers price and order material by. A 2,500 sq ft roof is 25 squares. Measure the roof, not the floor, and confirm the count before you finalize.

How do I handle bad decking I cannot see until tear-off?

Put a per-square-foot decking allowance in the estimate. You cannot see rot until the old roof is off, so pricing a rate for replacement up front turns a surprise into a documented line instead of an argument.

Should I take a deposit on a roofing job?

Yes. Roofing is material-heavy and high-value, so take a deposit to schedule with the balance on completion, and document any post-tear-off decking as a change order.

Related tools & guides

QuoteAnyJob is a quoting and planning tool, not legal or tax advice. Published 2026-07-26.